I had booked a house with HDIL Majestic Towers, Nahur in the year 2011 as till date we have not got the possession of our homes, and as per the agreement possession date was committed as December 2013 by HDIL, but there is not transparency shown by the builder towards the buyers people have invested there hard earned money. We also went to HDIL site and found there is no progress in the work as work is totally stopped. We met the Manager and asked her about the progress of work, she replied there is no work started as on today. Most probably they will start the work by end of this month. Of course there is nothing new in this reply as this is their standard answer. I had requested our core committee to take some action against the builder, as they dont have any intention of starting the work in near future.