Dear all
I have booked an apartment in Kaveri Tower with Maghun builder at Mahagunpuram ph-2 at nh 24. I was committed the possession of flat in DEC 2015. Now its Apr 2017, still waiting for the possession. I visited site yesterday and surprised to see that there is no work on progress for almost last two months. No satisfactory answer from the construction staff. Merely 90-100 labours were working there. In present scenario it seems that builder is not willing to provide possession for next one year too. We also commited penalty for delay, which also builder is not paying according to agreement. I have written so many emails to handingover email but I have not even received a single reply from their side. I spoke to Mr Piyush so many times but he never give satisfactory answer. So I request you all please take a strict step against the builder if we want to get our flat. We all should get together to put pressure on builder.
NK Tomar
Kaveri Tower