Good project at mercy of promoters

Approx 50% flats are sold but still no work is started.project was launched in dec 2020 with possession date of May 2026.we are in 2024 and no work started. When we used call CRM they used to inform us it is on track. But suddey we got from kalpataru that they want to extend the project timeliness and want our consent..why any buyer will give consent???


So don’t know how the project will proceed..